| 
      
     | 
      | 
    ![]()  | 
      | 
    
      
        
| 
Prefabricated Modules | 
         
        
| 
 
    | 
         
        
| 
    | 
         
        
| 
The capsule 
dimensions were 2.5 m x 4 m x 2.5 m. The capsules were fabricated at the factory 
and fitted out including utilities, interior fittings etc., and were attached to 
the concrete towers. Each capsule was attached to the shaft by 4 high-tension 
bolts and were independently cantilevered from the shaft so that any capsule may 
be easily removed without affecting the others. The form of the capsule was 
simple and the major structure was an all-welded lightweight steel-truss box. 
The exterior was covered with galvanized, rib-reinforced steel panels. After 
processing, the panels were coated with rust-preventative paint, and finished 
with a coat of a glossy spray, Kenitex. | 
         
        
| 
 
   | 
         
        
  | 
         
        
 | 
         
        
| 
The Cores | 
         
        
 | 
         
        
| 
They were 
made of a steel frame and reinforced concrete, rigid-frame structure. From the 
basement to the second floor ordinary concrete was used, but above these levels 
lightweight concrete was used. Shuttering consisted of large panels the height 
of a single storey of the tower. In order to make early use of the staircase, 
precast concrete was used in the floor plates and the elevator shafts. By using 
a policy whereby steel-frame work was done for two days and precast concrete 
work on the following two days, the designers were able to prepare a completely 
operational staircase by the time the frame-work was finished. Construction of 
the elevators on-site was shortened by incorporating the 3D frames, the rails, 
anchor indicator boxes, etc., in the precast concrete elements and by employing 
prefabricated cages. | 
         
        
  | 
         
        
| 
  | 
         
        
| 
Construction Phases | 
         
        
 | 
         
        
| 
The 
construction process included 2 categories: | 
         
        
 | 
         
        
- On-site 
construction included the 2 towers 
  
and their energy-supply systems and 
  
equipment. | 
         
        
|   | 
         
        
- Off-site 
fabrication: factory production of 
  
the capsule 
parts and assembly of the 
  
parts. | 
         
        
  | 
         
         
     |