Notable Features | 
         
        
 | 
 | 
         
        
  | 
Prefabricated modular residential construction | 
         
        
  | 
Flexibility | 
         
        
          | 
           
             | 
         
        
| 
Basic Information | 
         
        
          | 
           | 
         
        
          | 
          
          
          Location 
          
          : | 
         
        
          | 
          London, UK | 
         
        
          | 
          Building Type : | 
         
        
          | 
          Residential | 
         
        
          | 
          
          Contract 
          Period : | 
         
        
          | 
           
          Contract duration 27 
          weeks (02/1999 to 08/1999) excluding manufacture period for modules.  
          Total completion time 44 weeks  | 
         
        
          | 
          
          
          Contract Sum
          : | 
         
        
          | 
          Construction cost 
          £2,335,000 
          and the average cost per unit 
          
          £77,800 | 
         
        
          | 
          Gross External 
          Floor Area 
          : | 
         
        
          | 
          2150 m2 | 
         
        
          | 
          Client : | 
         
        
          | 
          Peabody Trust | 
         
        
          | 
          Architect : | 
         
        
          | 
          Cartwright-Pickard | 
         
        
          | 
          Main Contractor : | 
         
        
          | 
          Kajima | 
         
        
          | 
          Manufacturer : | 
         
        
          | 
          Yorkon | 
         
        
          
          
            | 
         
        
          | . | 
         
        
| 
Overview | 
         
        
| 
  | 
         
        
| 
 
   | 
         
        
| 
The 5-storey 
high residential building comprises 16 one-bedroom apartments assembled from two 
modules, and 14 two-bedroom apartments assembled from three modules. No 
additional structural frame was provided. | 
         
        
| 
  | 
         
        
| 
The modules 
were prefabricated in the factory and positioned on site. The units were stacked 
in two wings, spreading outwards from a central, circular staircase core which 
was constructed in a traditional way. The approach resulted in swifter 
construction time, and site disruption was kept to a minimum. The development 
was completed in half the time it would have taken using conventional 
construction methods. | 
         
        
  | 
         
        
| 
  | 
         
        
| 
Awards | 
         
        
| 
  | 
         
        
  | 
Building of the year - Royal Fine Art Commission | 
         
        
  | 
Structural Steel Award - Corus | 
         
        
  | 
Housing Design Award - RIBA et al. | 
         
        
  | 
American Institute of Architecture Award | 
         
        
| 
  | 
         
        
  | 
         
        
| 
  | 
         
        
| 
Contractor's 
Contract | 
         
        
| 
  | 
         
        
| 
Kajima | 
         
        
| 
www.kajima.co.uk | 
         
        
  | 
         
        
| 
  | 
         
        
| 
Sources | 
         
        
| 
  | 
         
        
  | 
Prefabricated housing in the UK, BRE Information 
Paper IP16/01 | 
         
        
  | 
Modular manufacture, The Architect's Journal, 17 
February 2000 | 
         
        
  | 
Bell, J., Murray Grove Flats, Architectural design 
Vol. 70 No. 4, The Transformable House, 2000 | 
         
        
  | 
         
         
     | 
      | 
    ![]()  | 
      | 
    
      
     |