| 
Notable Features | 
         
        
  | 
Semi precast 
slab and beams | 
         
        
  | 
Precast 
staircases | 
         
        
  | 
Composite 
columns with steel formwork | 
         
        
  | 
Aluminum and 
steel formwork | 
         
        
  | 
Hardiwall 
partitions | 
         
        
  | 
Use of jump 
lift | 
         
        
  | 
Reusable 
safety system | 
         
        
          | 
           | 
         
        
          | 
           
             | 
         
        
| 
Basic Information | 
         
        
          | 
          
          
          Location: | 
         
        
          
          Taikoo Place, 979 
          King's Road,  
          Quarry Bay, Hong Kong | 
         
        
          | 
          Building Type : | 
         
        
          | 
          Office | 
         
        
          | 
          
          Contract 
          Period: | 
         
        
          | 
           
          29/10/2001 - 
          21/04/2003 (540 days)  | 
         
        
          | 
          
          
          Contract Sum : | 
         
        
          | 
          Approximately HK$420 
          million | 
         
        
          | 
          
          
          Site Area : | 
         
        
          | 
          6,700 sqft | 
         
        
          | 
          Gross Floor Area : | 
         
        
          | 
          Total construction floor area:31,140 m2 | 
         
        
          | 
          Typical Floor Area 
          : | 
         
        
          | 
          795 m2 | 
         
        
          | 
          Client : | 
         
        
          | 
          Taikoo Place Holdings Ltd. | 
         
        
          | 
          Client's Project 
          Manager : | 
         
        
          | 
          Swire Properties Ltd. | 
         
        
          | 
          Architect : | 
         
        
          | 
          Wong & Ouyang (HK) Ltd. | 
         
        
          | 
          Structural 
          Engineer : | 
         
        
          | 
          Maunsell Structural Consultants Ltd. | 
         
        
          | 
          E&M Consultant : | 
         
        
          | 
          Meinhardt (M&E) Ltd. | 
         
        
          | 
          Quantity Surveyor 
          : | 
         
        
          | 
          Levett & Bailey Chartered Quantity 
          Surveyors Ltd. | 
         
        
          | 
          Main Contractor : | 
         
        
          | 
          Hsin Chong Construction (Asia) Ltd. | 
         
        
          
          
            | 
         
        
          | . | 
         
        
| 
Overview | 
         
        
| 
This 
36-storey grade A office building includes a 2-storey podium and a 1-storey M/E 
floor. The total construction floor area is 31,140m2, and each typical floor 
area is 795m2. Typical floors construction (4 days cycle) is split into two 
portions: semi-precast portion and in-situ portion. The in-situ portion is two 
floors ahead the precast portion. 95% BS Components off-site prefabricated. | 
         
        
| 
  | 
         
        
| 
 
   | 
         
        
| 
  | 
         
        
| 
Precast 
portion: | 
         
        
  | 
Precast floor 
from 3/F to 21/F: 11 beams, 44 planks, and 3 stair modules per floor. | 
         
        
  | 
Precast floor 
from 22/F to 36/F: 12 beams, 48 planks, and 3 stair modules per floor. | 
         
        
| 
  | 
         
        
  | 
         
        
| 
  | 
         
        
| 
In this 
project, the choice for precast construction method is due to its lower cost and 
shorter construction period. Although the technology used is more expensive than 
traditional methods, the total cost is lower because of the shorter construction 
period. The in situ methods would have extended the construction for 2 months. | 
         
        
| 
  | 
         
        
| 
 
   | 
         
        
  | 
         
        
| 
   . 
           | 
         
        
Typical Floors Construction  
(4 days cycle) | 
         
        
          | 
           | 
         
        
          | 
           
          
             | 
         
        
          | 
           | 
         
        
          
          
             | 
         
        
          | 
           
             | 
         
        
| 
   
    | 
         
        
| 
Semi-precast Planks | 
         
        
| 
   
  
     | 
         
        
 | 
         
        
| 
Semi-precast 
planks are delivered on site on Day 2, and hoisted and installed on Day 3. The 
plank dimensions are: max. Span 2.4 x 4.9 m2, and the max. Weight: 3.1 tons | 
         
        
 | 
         
        
   | 
         
        
 | 
         
        
  | 
         
        
 | 
         
        
  | 
         
        
| 
    | 
         
       
     | 
      | 
    ![]()  | 
      | 
    
      
        
| 
Semi-precast 
Beams | 
         
        
| 
 
Semi-precast 
beams are delivered on site on Day 2, and hoisted and installed on Day 3. The 
beam dimensions are: max Span 16 m, 575 mm depth, and max. Weight 10 tons.  | 
         
        
| 
    | 
         
        
| 
 
    | 
         
        
  | 
         
        
|   | 
         
        
| 
Precast Staircases | 
         
        
| 
Precast 
staircases are hoisted and installed on Day 1. The staircase dimensions are: max 
span: 6.9 m, and max. Weight 10.8 tons. | 
         
        
|   | 
         
        
   
  | 
         
        
  | 
         
        
| 
    | 
         
        
| 
Columns | 
         
        
| 
Steel fixing 
of columns, installation of steel column formworks and concreting (22m3) are 
done on Day 2. | 
         
        
| 
  | 
         
        
    
  | 
         
        
  | 
         
        
|   | 
         
        
| 
Aluminum and Steel Formworks | 
         
        
|   | 
         
        
   
  | 
         
        
|   | 
         
        
| 
Aluminum and 
steel formworks are used for the in-situ portion. Refer to the typical floors 
construction (4 days cycle) table for details. | 
         
        
| 
 
   | 
         
        
| 
 
  
   | 
         
        
  | 
         
        
          |   | 
         
        
| 
Hardiwall | 
         
        
| 
 
Hardiwall 
system is used for internal partition.  | 
         
        
|   | 
         
        
| 
  
  | 
         
        
  | 
         
        
          |   | 
         
        
| 
Jump Lift | 
         
        
| 
 
Definition:
 
Using constructed lift shafts and permanent lift components to provide builder’s 
lift services during construction stage.  | 
         
        
          | 
           | 
         
        
          | 
          
          Advantages: | 
         
        
          
          
            - 
            
            
            Safety, as builder’s lift is located inside lift shaft and not 
            outside.  
            - 
            
            
            Noise reduction, minimizing disturbance to neighborhood.  
            - 
            
            
            Accelerating internal finishing and installation works.  
            - 
            
            
            Avoiding deferred works to external wall finishing.  
           
           | 
         
        
          | 
          
          Characteristics | 
         
        
          | 
          
           | 
         
        
          
          
            | 
         
        
          | 
           
           
          Cost difference of builder’s works: 
          Cost (A) – Cost (B) = $89,500 
          1 jump lift cost around $450,000, additional cost for using 1 jump 
          lift: 
          
          
          $450,000 + $89,500 = $539,500  | 
         
        
  | 
         
        
| 
Reusable 
Safety Systems | 
         
        
| 
 
All the safety 
systems are reusable and easy to assemble: 
   | 
         
        
          | 
          
             
            
              
            
            
              
           | 
         
        
            | 
         
        
| 
Contact of 
Contractor | 
         
        
| 
 
Hsin Chong Construction Co. 
Ltd. 
8/F Hsin Chong Center 
107-109 Wai Yip Street 
Kwun Tong, Kowloon 
Hong Kong 
www.hsinchong.com  | 
         
        
  | 
         
        
          |   | 
         
         
     |