| Notable Features |  
        
          |   |  
        
            | 
          Application of
            steel formwork |  
        
            | 
          Application of
            UPVC formwork |  
        
            | 
          Application of
            Timber formwork |  
        
            | 
          On-site
            sorting of waste |  
        
            | 
          Reuse
            of steel hoarding |  
         
        
      
 
        
        
          | Basic 
            Information |  
        
          |   |  
        
            | 
          Location: Happy
            Valley |  
        
            | 
          Building Type: Residential  |  
        
            | 
          Contract Period:
            494 days |  
        
            | 
          Gross
            Floor Area: 13,900m2 |  
        
            | 
          Client:
            Dorfit Properties Ltd. |  
        
            | 
          Architect: Chung
            Wah Nan Architects Ltd. |  
        
            | 
          Structural Engineer:
            Harris & Sutherland Consulting Engineers |  
        
            | 
          E&M
            Consultant: Parsons Brinckerhoff (Asia) Ltd. |  
        
            | 
          Quantity Surveyor: Levett
            & Bailey Chartered Quantity Surveyors |  
        
            | 
          Main Contractor: Hsin
            Chong Construction (Asia) Ltd. |  
        
            | 
          Contract Sum: Approx.
            HK$ 210 million |   
        
       
     | 
      | 
    ![]()  | 
      | 
    
      
        
        
          | Steel
            Formwork |  
        
          |   |  
        
          
            
              
                | Steel
                  formwork was used for the circular columns with diameter larger
                  than 1 metre to maintain a more rigid formwork for concreting.
                  As the building is in the shape of an ellipse, steel formwork
                  was also adopted to construct the edge beams at the frontage of
                  the typical floors such that a better quality of curved
                  surface could be formed. In order to achieve a 5 day floor
                  cycle, the steel formwork for the edge beams were of handy
                  type since the tower crane had been fully occupied for loading
                  material and concreting. The steel formwork was scrapped
                  for sale after completion. | 
               
             
           |  
         
      
        
          |   | 
         
        
          | 
              
  | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          | UPVC Formwork | 
         
        
          |   | 
         
        
          | 
            UPVC formwork was used for
            circular columns with diameter of about 1 metre. High strength
            concrete was adopted for podium floor. Since the UPVC formwork could
            not
            be reused after striking, there was no need to hurry with striking
            the formwork for the next floor, the high strength concrete could be
            kept in the formwork for curing for 5 days.
           | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          | Timber Formwork | 
         
        
          |   | 
         
        
          | 
            Timber formwork was used for
            constructing the non-typical area and the floor slab.
           | 
         
        
          |   | 
         
        
          | 
              
          
  | 
         
       
      
        
        
          | 
            Contact
                  of Contractor
           |  
        
          | 
             
           |  
        
          | 
            Hsin Chong Construction (Asia)
            Ltd.
           |  
        
          | 
            Hsin Chong Center, 107-109 Wai
            Yip 
           |  
        
          | 
            Street, Kwun Tong, Kowloon
           |  
        
          | 
            Tel:
            (852) 2579 8238
           |  
        
          | 
            Fax:
            (852) 2516 9430
           |  
        
          | 
             
           |  
        
          | 
               
           |  
         
     |