Prefabricated Modules | 
        
        
| 
  | 
        
        
| 
The 3.6m wide 
modules were fully fitted out off-site at the factory with all plumbing, 
electrics, doors, windows, bathrooms, kitchens, and tiling pre-installed. The 
modules weighed up to 11 tonnes each. | 
        
        
| 
  | 
        
        
| 
The 
foundations were executed on site. The façades were clad in Western red cedar. 
The walkways were made of prefabricated steel and precast concrete decking, and 
balconies were made of steel and timber.  | 
        
        
  | 
        
        
 | 
        
        
| 
Construction Phases | 
        
        
| 
 | 
        
        
| 
The programme 
times were reduced by up to 50%. | 
        
        
| 
 | 
        
        
| 
Stage 1 – Module manufacture | 
        
        
| 
48 steel 
framed modules were manufactured and fitted out at the factory in York, while 
foundations were progressed on site.  | 
        
        
| 
 | 
        
        
| 
Stage 2 – Installation of modules on site | 
        
        
| 
The modules 
were transported and craned into position on site within a few days. The roof 
was then installed. | 
        
        
| 
 | 
        
        
| 
Stage 3 – Access deck assembly and installation of cladding | 
        
        
| 
The precast 
concrete walkways and the steel/timber balconies were fixed to the modules 
on-site, and external cladding installed. The lift and staircase towers was put 
in place. | 
        
        
| 
 | 
        
        
| 
Stage 4 – Completion of external works | 
        
        
| 
Landscaping 
in the courtyard, car park and cycle storage facility were completed. | 
        
        
  | 
        
        
| 
  | 
        
        
| 
Photos | 
        
        
| 
 | 
        
        
| 
Photos and 
web cam are available on the following web site: | 
        
        
| 
 
www.yorkon.com/sixthavenue  | 
        
        
  |