| Process | 
          Traditional
            Methods | 
          Low-Waste Technologies | 
        
        
           
            Building Design | 
           
              | 
           
            Use of materials size does not correspond with the dimensions in
            the building | 
           
              | 
           
            With the standard modular approach, walls and slabs are standardized
            in both size an shape, being interchangeable between different
            building types | 
        
        
          |    | 
            | 
          
             Building
            components not standardized  | 
            | 
          
             Standardized
            building components  | 
        
        
          |    | 
            | 
          Down-stand
            beams and columns detrimental to large panel formwork system
            construction | 
            | 
          Walls
            and flat slabs only, no down-stand beams and columns | 
        
        
          |    | 
            | 
          Specifications
            exceed the performance required | 
            | 
          Modification
            of specifications to suit the contractor’s available equipment and
            materials | 
        
        
          |     | 
            | 
          Significant
            unnecessary mid-project variations | 
            | 
          Less
            design variation | 
        
        
           
            Formwork | 
           
              | 
           
            Conventional timber formwork | 
           
              | 
           
            Large steel panel forms | 
        
        
          |    | 
            | 
          Double
            the cost of using steel panel in long run | 
            | 
          High
            initial cost but balanced by the long terms savings in timber
            formwork | 
        
        
          |    | 
            | 
          Labour
            intensive for erecting and striking formwork | 
            | 
          Less
            labour force required for erecting and striking formwork | 
        
        
          |    | 
            | 
          
             Longer
            construction duration  | 
            | 
          
             High
            efficiency, twice faster than timber formwork system  | 
        
        
          |    | 
            | 
          Plastering
            need for leveling concrete surface | 
            | 
          Better
            quality concrete products, concrete surfaces suitable for applying
            tiles and paints directly | 
        
        
          |    | 
            | 
          Reused
            8-15 times, several sets of timber forms needed for a high-rise
            block | 
            | 
          Reused
            over 100 times, one set of forms sufficient to complete a block and
            can be reused in another sites | 
        
        
          |    | 
            | 
          Hand
            lift timber board from floor to floor | 
            | 
          Tower
            cranes needed for lifting formwork | 
        
        
          |    | 
            | 
          Considerable
            timber waste produced | 
            | 
          Waste
            steel scrapped for recycling, less waste produced | 
        
        
           
            Concrete Work | 
           
              | 
           
            In-situ placement | 
           
              | 
           
            Precast concrete | 
        
        
          |    | 
            | 
          
             Time
            consuming  | 
            | 
          
             Shorter
            construction time  | 
        
        
          |    | 
            | 
          Higher
            labour cost | 
            | 
          Higher
            initial cost but relative cheaper for large quantity | 
        
        
          |    | 
            | 
          Poor
            quality, honeycombing often occurs | 
            | 
          Mass
            production, high degree of quality control | 
        
        
          |    | 
            | 
          Plastering
            required before applying tiles and paints | 
            | 
          Elements
            usually completed with necessary fixtures and finishes, no need for
            further finishing works | 
        
        
          |    | 
            | 
          More
            waste produced | 
            | 
          About
            30% less waste than in-situ concreting | 
        
        
           
            Masonry Work | 
           
              | 
           
            Brick walls or concrete block walls | 
           
              | 
           
            Internal drywall partitions | 
        
        
          |    | 
            | 
          
             Lower
            materials cost but higher labour cost  | 
            | 
          
             Higher
            materials cost but lower labour cost  | 
        
        
          |    | 
            | 
          High
            skill levels | 
            | 
          Easy
            to install, low skill levels | 
        
        
          |    | 
            | 
          Thick
            layer of plaster needed | 
            | 
          Smooth
            surface and no plastering needed | 
        
        
          |    | 
            | 
          Time
            consuming | 
            | 
          Four
            times faster than masonry work plus plastering | 
        
        
          |    | 
            | 
          More
            waste produced | 
            | 
          Wet
            trade not involved, hence less waste generated | 
        
        
          |    | 
            | 
          Walls
            with higher strength | 
            | 
          Walls
            with lower strength | 
        
        
           
            Plastering | 
           
              | 
           
            Conventional mortar cement | 
           
              | 
           
            Spray Plaster | 
        
        
          |    | 
            | 
          
             Manual
            Applying  | 
            | 
          
             Mechanical
            spraying  | 
        
        
          |    | 
            | 
          Suitable
            for rough wall surface, further leveling is required | 
            | 
          Suitable
            for smooth wall surface, further leveling is not required | 
        
        
          |    | 
            | 
          Time
            consuming | 
            | 
          Faster
            construction | 
        
        
          |    | 
            | 
          Labour
            intensive | 
            | 
          Less
            labour demand | 
        
        
          |    | 
            | 
          More
            waste generated | 
            | 
          Less
            waste generated | 
        
        
           
            Hoarding | 
           
              | 
           
            Timber hoarding | 
           
              | 
           
            Steel hoarding | 
        
        
          |    | 
            | 
          
             Cheaper
            materials cost, easy to erect  | 
            | 
          
             Expensive
            and demand higher labour force for erection, but safe for passer-by  | 
        
        
          |    | 
            | 
          Less
            durable, about 2 years lifetime | 
            | 
          More
            durable, about 4.5 years lifetime | 
        
        
          |    | 
            | 
          Low
            reusability, discarded after used once | 
            | 
          High
            reusability, waste steel scrapped for recycling | 
        
        
          |     | 
            | 
          More
            timber waste produced | 
            | 
          70%
            less waste | 
        
        
           
            Scaffolding | 
           
              | 
           
            Conventional bamboo scaffold | 
           
              | 
           
            Gondola with Passenger Lift | 
        
        
          |    | 
            | 
          
             Lower
            initial cost  | 
            | 
          
             Higher
            initial cost, but balanced by saving in materials cost in the long
            run  | 
        
        
          |    | 
            | 
          High
            labour cost | 
            | 
          Less
            labour force required | 
        
        
          |    | 
            | 
          Less
            safe for workers | 
            | 
          More
            safe for workers | 
        
        
          |    | 
            | 
          More
            bamboo waste produced | 
            | 
          80%
            less waste |