| Notable Features |  
        
          |   |  
        
            | 
          Construction waste
            reduction/recycling program |  
        
            | 
          Reduced Construction waste due
            to use of factory manufactured aluminium formwork panels |  
        
            | 
          Application of
            value engineering in terms of slab and wall formwork |  
        
            | 
          Use of system
            formwork |  
        
            | 
          Use of bay windows
            and A/C hoods  |  
        
            | 
          Aluminium formwork
            panels were
            used for casting the structural shear walls |  
        
            | 
          Reuse of aluminium
            formwork panels |  
        
            | 
          V-shaped prop head
            system |  
         
        
      
 
        
        
          | Basic 
            Information |  
        
          |   |  
        
            | 
          Location: Tseung
            Kwan O |  
        
            | 
          Site Area: 500,000
            sq ft |  
        
            | 
          Building Type: 15
            luxurious residential towers in three phases |  
        
            | 
          Contract Period:
            750 days for phase 1 |  
        
            | 
          Facilities: Club
            house, swimming pool, tennis court, children's play ground, car park
            etc. |  
        
            | 
          Client: Arrowtown Assets Limited |  
        
            | 
          Architect: Wong
            Tung & Partners Ltd. |  
        
            | 
          Quantity Surveyor: Davis
            Langon & Seah Hong kong Ltd. |  
        
            | 
          Structural Engineer:
            Joseph Chow & Partners Ltd. |  
        
            | 
          E&M
            Consultant: Meinhardt (M&E) Ltd. |  
        
            | 
          Main Contractor: Sanfield
            Building Contractors Ltd. |  
        
            | 
          Building costs: HK$
            1600 million for phase 1  |   
        
      
 
        
        
          | Overview |  
        
          |   |  
        
          | 
             The Tseung Kwan O TKOTL 55
            development, named as Ocean Shore with a site area of over 500,000
            square feet, consisted of 15 luxurious residential towers to be
            constructed in 3 phases. 
             
            
            Following to the client's requirement,
            the architect emphasized his design to capture the greenery
            surrounded
            either along the hillside or the lush plantation of the landscaped
            podium garden. A 3 levels podium structure was therefore designed to
            provide space for various facilities including the clubhouse,
            swimming pool, tennis court, children's play ground, car park
            etc. 
             
            It was the developer's vision
            to provide the best not only the large scale master layout plan but
            also the quality of the apartment to the residents lived there.
             
            
            
              
                | Plastering and Finishing
                 | 
               
              
                |   | 
               
              
                
                  
                    
                      | The main
                  advantage of aluminium formwork was good alignment and
                  verticality with good concrete finish surface which minimised
                  the cost on plastering and finish work. High quality Aluminium Formwork
                        Panels ensure 
                  consistency of dimensions. On the removal of the formwork mould, a high quality 
                  concrete finish was produced to accurate tolerances and 
                  verticality. The high tolerance of the finish means that no
                        thick plastering was required. Typically a 3mm to 4mm skim 
                  coat was applied internally prior to finishing and a 6 mm build 
                  up coat prior to laying 
        tiles. | 
                     
                   
                 | 
               
              
                |   | 
               
              
                | 
                     
                 | 
               
              
                | Contact
                  of Contractor
                 | 
               
              
                |   | 
               
              
                | Sanfield
            Building Contractors Ltd.
                 | 
               
              
                | 44/F,
                  Sun Hung Kai Center,
                 | 
               
              
                | 30
                  Harcourt Road, Wanchai,
            Hong Kong.
                 | 
               
              
                | Tel:
            (852) 2827 8111
                 | 
               
              
                | Fax:
            (852) 2827 0717
                 | 
               
              
                | 
                 | 
               
              
                | 
                     
                 | 
               
             
           |   
     | 
      | 
    ![]()  | 
      | 
    
      
        
        
          | Slab and Wall System |  
        
          |   |  
        
          
            
              
                | It had been the
            client's intention to use system formwork for
            a better quality concrete finish and good alignment and verticality.
            However with the complex architectural features, bay windows and A/C
            hoods etc. were adopted in this project, the use of large steel panel or
                  precast concrete panel was not an option for the construction
                  in this project. | 
               
             
            
            
              
                |   | 
               
              
                | The engineer was requested to
            explore the possibility of using aluminium handset system formwork on
            both technical and cost effectiveness requirements. A simple handset
                  aluminium formwork was finally chosen to use on
            three residential blocks of phase 1 and majority of the aluminium
            formwork panels will be reused on the residential blocks of phase 2. The advantages of
                  aluminium formwork are:
                 | 
               
             
            
              
                |   | 
               
              
                  | 
                Good alignment and verticality | 
               
              
                  | 
                High finish
                  quality | 
               
              
                  | 
                No tower
                  crane required | 
               
              
                  | 
                Require
                  unskilled
                  labour force | 
               
              
                  | 
                Environmental
                  friendly | 
               
              
                  | 
                Speedy and
                  economical | 
               
              
                  | 
                Earlier
                  stripping of forms | 
               
             
           |  
         
      
      
        
        
          
            
              
                |   | 
                Timber
                  Formwork | 
                System
                  Formwork | 
               
              
                | 
                   Material 
                 | 
                
                   Timber and Plywood 
                 | 
                
                   All
                  Aluminium 
                 | 
               
              
                | 
                   Durability 
                 | 
                
                   20
                  times 
                 | 
                
                   120-150
                  times 
                 | 
               
              
                | 
                   Wastage 
                 | 
                
                   Yes 
                 | 
                
                   No 
                 | 
               
              
                | 
                   Quality 
                 | 
                
                   Subject
                  to Workmanship 
                 | 
                
                   Good 
                 | 
               
              
                | 
                   Labour 
                 | 
                
                   Skilled 
                 | 
                
                   Unskilled 
                 | 
               
              
                | 
                   Flexibility 
                 | 
                
                   More 
                 | 
                
                   Less 
                 | 
               
              
                | 
                   Cost 
                 | 
                
                   HK$100-140/m2 
                 | 
                
                   HK$140-180/m2 
                 | 
               
             
           |  
        
          |   |  
        
          | 
               
           |  
        
          | Steel
            Column Formwork |  
        
          |   |  
        
          | Steel column
            formwork was used to construct the large circular column as shown in
            the figure below. |  
        
          |   |  
        
          | 
            
           |  
        
          |   |  
        
          | Steel forms
            are very durable and can be recycled many times. Steel forms produce
            a better quality concrete product. |  
        
          |   |  
        
          | 
            
           |  
        
          |   |  
        
          | 
               
           |  
        
          | Waste Management |  
        
          |   |  
        
            | 
          Material control |  
        
            | 
          Reusable material adopted-aluminium
            formwork |  
        
            | 
          Surplus steel bars
            were stored for
            reuse |  
        
            | 
          Job-site
            recycling |  
        
          | 
              
  | 
         
         
     |