| Notable Features |  
        
          |   |  
        
            | 
          Construction waste
            reduction/recycling program |  
        
            | 
          Reduced
            construction waste due
            to use of factory manufactured precast concrete elements |  
        
            | 
          Application of
            large panel steel formwork |  
        
            | 
          Use of drywall for
            the internal partitions |  
        
            | 
          Use of
            semi-precast slab |  
        
            | 
          Use of precast facade |  
        
            | 
          Use of precast
            staircase |  
        
            | 
          Use of precast
            cooking bench |  
        
            | 
          Use of
            prefabricated door sets  |  
        
            | 
          Use of spray plastering |  
        
            | 
          Use of gondola to
            apply external finishes |  
        
            | 
          Use of steel
            fabric reinforcement |  
        
            | 
          On-site sorting of
            waste |  
        
            | 
          Reuse of steel formwork panels |  
        
            | 
          Reuse of surplus
            steel bars |  
        
            | 
          Reuse of steel
            hoarding |  
         
        
      
 
        
        
          | Basic 
            Information |  
        
          |   |  
        
            | 
          Location: Cheung Sha Wan
            West |  
        
            | 
          Building Type: Residential  |  
        
            | 
          Contract Period: 2
            years |  
        
            | 
          Scheduled Completion: Nov
            2000 |  
        
            | 
          Client: The Hong
            Kong Housing Authority |  
        
            | 
          Architect: Ho
            & Partners Architects, Engineers & Development Consultants
            Ltd. |  
        
            | 
          Structural Engineer:
            Mitchell, McFarlane, Brentnell & Partners International Ltd. |  
        
            | 
          E&M
            Consultant: Twin Way Consulting Engineers Ltd. |  
        
            | 
          Quantity Surveyor: C.
            S. Toh & Sons & Associates |  
        
            | 
          Main Contractor: Yau
            Lee Construction Co., Ltd. |  
        
            | 
          Contract Sum: HK$
            750 million |   
        
      
 
        
        
          | Overview |  
        
          |   |  
        
          | The
            Cheung Sha Wan West Phase-II was a residential building project and
            the following major items were executed under this contract: |  
        
          |   |  
        
          
            
              
                  | 
                1 no. 41 storey Harmony
                1 (Option10), approximately 48 x 53 m overall on plan and
                approximately 113 m high from ground floor to main roof level.
                The long wing of each block is linked to its short wing with a
                90o angle link core approximately 17 x 17 m overall on plan. The
                block contains 79 no. Type 1P, 240 no. Type 1B, 320 no. Type 2B,
                80 no. Type 3B rental domestic units in 40 domestic upper
                floors. | 
               
              
                  | 
                2 no. 41 storey Harmony 1
                (Option 10) Blocks in Handed Version, each block approximately
                48 x 53 m overall on plan and approximately 113 m high from
                ground floor to main roof level. The long wing of each block is
                linked to its short wings with a 90o angle link core
                approximately 17 x 17 m overall on plan. The blocks contain 158
                no. Type 1P, 480 no. Type 1B, 640 no. Type 2B, 160 no. Type 3B
                rental domestic units in 40 domestic upper floors. | 
               
              
                  | 
                1 no. 21 storey new
                Harmony Annex 3 (Option 1), approximately 11 x 22 m overall on
                plan and approximately 59m high ground floor to main roof level.
                The block contains 140 no. Type 1P rental domestic units in 20
                domestic upper floors. | 
               
              
                  | 
                2 no. 21 storey new
                Harmony Annex 4, approximately 21 x 17 m overall on plan and
                approximately 59 m high ground floor to main roof level. The
                blocks contain 320 no. Type 1P rental domestic units in 20
                domestic upper floors. | 
               
              
                  | 
                All associated drainage
                and external works, including lorry parking areas, roads
                emergency and service access, play areas, ball courts, covered
                walkways, refuse collection point, junk collection point,
                pavilion and landscape planters. | 
               
             
           |  
        
          
            
              
                |   | 
                  | 
               
              
                |   | 
                
                    
                
  | 
               
              
                |   | 
                Plastering and Finishing
                 | 
               
              
                |   | 
                  | 
               
              
                | 
                   
                 | 
                
                  
                    
                      | Since
                        the precast wall and floor slabs, as well as the factory
                        made internal walls provided very smooth and accurate
                        surfaces, thick plaster was not necessary. Plaster
                        dropping on floor during the finishing process,
                        sometimes accumulate to a thickness of 30mm over the
                        whole floor area, can hardly be avoided in traditional
                        cement sand plaster. | 
                     
                    
                      |  
                        
                         However, with spray plastering the
                        same was not happened in this project. It also has the
                        advantage of higher productivity and lower demand of
                        labour. 
                       | 
                     
                   
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                
                  
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                Gondola
                  was used to apply external finishes. This saved the waste of
                  bamboo scaffolding. | 
               
              
                |   | 
                  | 
               
              
                |   | 
                
                     
                 | 
               
              
                |   | 
                Waste Management | 
               
              
                |   | 
                  | 
               
              
                |   | 
                  | 
                On-site
                  sorting of waste | 
               
              
                |   | 
                  | 
               
              
                |   | 
                On-site
                  sorting was partially performed. Distributed Separation was adopted. The following materials
                  were sorted
                  out: | 
               
              
                |   | 
                  | 
               
              
                |   | 
                
                  
                    
                      | 
                          
  | 
                      Surplus
                      reinforcement – transported to the ground level by hoist
                      or tower crane | 
                     
                    
                      | 
                          
  | 
                      Packaging material
                      – transported by hoist | 
                     
                    
                      | 
                          
  | 
                      Rubble + foam +
                      plastic conduit – transported by refuse chute | 
                     
                   
                 | 
               
              
                |   | 
                
                   
                 | 
               
              
                |   | 
                It
                  had been considered that the rubble/aggregate could be as
                  hardcore (size<200mm) for backfilling or sub-base for road.
                  However, there was no storage space for the rubble/recycled
                  aggregate. | 
               
              
                |   | 
                  | 
               
              
                |   | 
                  | 
                Material
                  Control | 
               
              
                |   | 
                  | 
               
              
                |   | 
                
                  
                    
                      | 
                          
  | 
                      The sub-contractors
                      were required to supply labourers as well as materials
                      such that they would reduce wastage of raw materials as
                      much as they could. | 
                     
                    
                      | 
                          
  | 
                      Where the main
                      contractor supplied raw materials, sample floor/flat was
                      used to estimate the materials required, thus ensuring the
                      control of materials. | 
                     
                   
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                  | 
                 Use
                  of recycled materials | 
               
              
                |   | 
                  | 
               
              
                |   | 
                
                  
                    
                      | 
                          
  | 
                      The
                  steel formwork had been used for another site already. It
                  would be reused or scrapped and transported to China for
                  resale depending on the condition of the material. | 
                     
                   
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                  | 
                
                   Reusable
                  materials 
                 | 
               
              
                |   | 
                
                   
                 | 
               
              
                |   | 
                
                  
                    
                      | 
                          
  | 
                      
                         surplus steel bars
                        were stored for reuse  | 
                     
                    
                      | 
                          
  | 
                      
                         steel hoarding  | 
                     
                    
                      | 
                          
  | 
                      
                         steel formwork  | 
                     
                    
                      | 
                          
  | 
                      
                         steel protective
                      canopy of standard size at 1/F – it was first used for
                      this contract  | 
                     
                   
                 | 
               
              
                |   | 
                  | 
               
              
                |   | 
                  | 
                
                   Steel
                  fabric reinforcement was used to reduce the waste 
                 | 
               
              
                |   | 
                
                     
                 | 
               
             
           |   
     | 
      | 
    ![]()  | 
      | 
    
      
        
        
          |  Wall System |  
        
          |   |  
        
          
            
              
                | Large panel
                  formwork was used to construct load-bearing walls of standard
                  domestic floors. Since all the wall formwork less than 7.5m
                  long was required to be cast in one piece, it minimised the number of
                  joints between formwork panels; therefore, less chance of
                  grout leakage or uneven surface finishes at joint which are
                  usually a norm for traditional timber formwork. For durability
                  and ease of maintenance of steel formwork, one set of formwork
                  can repetitively be used throughout the block. For instance,
                  one set of wallform was cyclically employed for the
                  construction of Harmony 1 housing block with four wings. At
                  the beginning, an 8-day floor cycle was adopted. As they had
                  got used to the technology, a 6-day floor cycle was
                  adopted.  | 
               
             
            
              
                |  
                 | 
               
              
                | 
                  
                 | 
               
              
                |  
                 | 
               
              
                | It was
                  anticipated that the cost of steel formwork would be more or
                  less the same when compared with timber formwork for this
                  project. The
                  cost of steel formwork was even cheaper when the cost of
                  carpenter was increased to HK$3,000 per manday in the past.
                 | 
               
             
           |  
         
      
        
          |   | 
         
        
          | 
               
           | 
         
        
          | Dry Wall | 
         
        
          |   | 
         
        
          | The
            internal partitions were built of factory made lightweight concrete
            panels. Joints were minimized by the use of large size
            floor-to-ceiling panels. Cutting was not necessary because the size
            of the panels was tailored to suit the building, thus the amount of
            waste that would be produced during construction was further
            minimized. The time required was also less than the traditional brick
            or block construction.  | 
         
        
          | 
               
           | 
         
        
          | 
            
           | 
         
        
          |   | 
         
        
          | The
            factory made panel gives very smooth and accurate surface finish.
            However, it might not be acceptable because of its lower strength in
            supporting point load and resistance to impact. | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          | Slab
            System | 
         
        
          |   | 
         
        
          | 
            Semi-precast slab was adopted to
            be the slab of each floor. 75mm thick precast slab was installed
            first at the floor level which served as the formwork for the 95mm
            thick in-situ concrete layer, thus forming a 170mm thick concrete
            floor. This saved the time in erecting and striking the timber
            formwork as well as forming a smooth ceiling finishes for the floor
            below. 
            
             The cost of the semi-precast
            slab is now competitive to the cost of timber formwork. However, the
            precast slab must be handled and transported with care to prevent
            cracking of the slab.
            | 
         
       
      
        
        
          |   |  
        
          | 
               
           |  
        
          | Precast
            Facade |  
        
          |   |  
        
          | The
            precast facade was manufactured in China and transported to the site
            for fixing. It was stored on the ground level and was hanged to the
            required floor by tower crane. The precast facade with projecting
            angle supports at both ends was placed in position on top of the
            structural wall. Inclined bracing fixed onto floor slab was installed
            to control the vertical alignment of the facade. Construction for
            wall followed. Then precast slab panels were installed with
            scaffolding supports. The top edge of the precast facade was right at
            the top level of the floor slab, such that the precast facade formed
            the stop end for the floor slab. |  
        
          |   |  
        
          | 
            
           |  
        
          |   |  
        
          | It
            is cost effective to use precast facade in mass production. |  
        
          | 
               
           | 
         
        
          | Precast
            Staircase | 
         
        
          |   | 
         
        
          | The
            precast staircase was constructed in 8 risers. According to the
            building layout, the staircase was enclosed by structural walls on
            two sides. The mid-landing was casted as in-situ with wall supports
            on both ends. Due to the smooth surface quality, no applied finishes would
            be necessary. A metal nosing strip was the only thing that was
            required to finish the stair. Naturally, construction waste was not
            arised. | 
         
        
          |   | 
         
        
          | 
            
           | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          | Precast
            Cooking Bench | 
         
        
          |   | 
         
        
          | Cooking
            benches were also prefabricated elements. Bench top was cladded with
            1 piece 0.8mm satin finish stainless steel sheet. The bench itself
            was of lightweight concrete and supported by 60mm concrete support,
            smooth finish and epoxy painted.  | 
         
        
          |   | 
         
        
          | 
            
           | 
         
        
          |   | 
         
        
          | The
            stainless steel sink was cast in lightweight concrete bed, 75mm
            thick, to afford strength to stand chopping and cutting. Earthing
            lugs were designed and built for both sink and bench. | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          | Prefabricated
            Doorsets | 
         
        
          |   | 
         
        
          | Prefabricated
            door frames and doors were used in this project. These doorsets saved temporary timber support for door frame, thus reducing waste. | 
         
        
          |   | 
         
        
          | 
               
           | 
         
        
          | Contact
                  of Contractor
           | 
         
        
          |   | 
         
        
          | Yau
            Lee Construction Co., Ltd. | 
         
        
          | 10/F.,
            Tower I, Enterprise Square, 9 Sheung Yuet Road, Kowloon Bay, Kowloon,
            Hong Kong | 
         
        
          | Tel:
            (852) 2753 4388
           | 
         
        
          | Fax:
            (852) 2753 4300
           | 
         
        
          | E-mail: info@yaulee.com
           | 
         
        
          | 
               
           | 
         
         
     |