| Notable Features |  
        
          |   |  
        
            | 
          Application of
            system formwork  |  
        
            | 
          Reuse of
            steel panels |  
        
            | 
          Use of
            precast staircase |  
        
            | 
          Use of
            precast bay windows |  
        
            | 
          Use of
            Hardi-Wall system |  
         
        
      
 
        
        
          | Basic 
            Information |  
        
          |   |  
        
            | 
          Location: Shau
            Kei Wan |  
        
            | 
          Building
            Type: Residential |  
        
            | 
          Contract Period:
            August 99 to July 2001 |  
        
            | 
          Client:
            Uttoxeter Ltd. |  
        
            | 
          Architect: Wong
            Tung & Partners Ltd. |  
        
            | 
          Structural Engineer:
            Ove Arup & Partners Ltd |  
        
            | 
          E&M
            Consultant: J. Roger Preston Ltd. |  
        
            | 
          Quantity
            Surveyor: Davis Langdon & Seah (HK) Ltd. |  
        
            | 
          Main Contractor: Dragages
            at Travaux Publics |  
        
            | 
          Contract Sum: HK$
            900 million |   
        
      
 
        
        
          | Overview |  
        
          |   |  
        
          | 
            The project involved the
            construction of four 49 to 56 storey high residential blocks with
            basement and clubhouse. There were 864 domestic units. |  
        
          | 
              |  
        
          | 
              
             
           |  
        
          
            
              
                | System
                  Formwork
                 | 
               
              
                |   | 
               
              
                | Steel
                  formwork was used to construct the structural walls of the
                  building while “Mivan” aluminum formwork was used to
                  construct the slabs, some of the bay windows and a few walls.
                  A 4-day concreting cycle was adopted after the contractor had
                  been familiarized with the construction technique. Speed is
                  one of the advantages of using system formwork. The formwork
                  can be reused for 100 times and waste is reduced. Besides a
                  better quality of surface finish is achieved. | 
               
              
                |   | 
               
              
                | 
                    
  | 
               
              
                | 
                   Storage
                  of aluminium formwork
                  | 
               
              
                |  
                 | 
               
              
                | 
                    
                
  | 
               
              
                | 
                   Aluminium
                  formwork
                  | 
               
              
                | 
                    
                
  | 
               
             
           |   
     | 
      | 
    ![]()  | 
      | 
    
      
        
        
          | Precast
            Elements | 
         
        
          |   | 
         
        
          | 
            Precast staircases and bay
            windows were adopted for this site. The cost was more or less the same
            as the in-situ method. The site was more tidy when compared with a
            site using in-situ method. A better quality of surface finishes was achieved. Both construction and finishing waste
            were reduced by
            adopting precast elements.
           | 
         
        
          |   | 
         
        
          | 
              
  | 
         
        
          | 
             Precast bay
            window 
           | 
         
        
          | 
               
           | 
         
        
          | Hardi-Wall System | 
         
        
          |   | 
         
        
          | 
            The HardiWall Solid Wall System
            is an internal non-loading bearing wall comprising light gauge
            galvanised steel stud framing, lined with HardiWall fibre cement
            sheets and filled with a proprietary lightweight concrete core mix.
            It is an Australian product.
           | 
         
        
          |   | 
         
        
          | 
              
  | 
         
        
          |   | 
         
        
          | The
            HardiWall System can provide the solid feel and sense of security
            traditionally associated with masonry walls. The surface finish of
            the wall is very smooth and flat and superior to traditional
            plastered walls. It has the advantage of greater ease of
            construction and thus increasing the speed of fit-out. There is
            potentially large savings in reduction of engineering dead loads as
            the system is approximately one third the weight of rendered masonry
            materials.  | 
         
        
          |   | 
         
        
          | 
            The HardiWall System removes wet
            trades and the necessity to chasing services and hence decreases the
            generation and disposal of waste and debris.General housekeeping is
            also improved by removing wet trades and minimizing debris.The
            HardiWall system is more expensive than traditional masonry wall by
            5-10%.
           | 
         
        
          |   | 
         
        
          | 
              
          
  | 
         
        
          | Contact
                  of Contractor
           | 
         
        
          |   | 
         
        
          | 
            Dragages at Travaux Publics (HK)
            Ltd. | 
         
        
          | 
            11/F, Island Place Tower, 510
            King's Road | 
         
        
          | 
            North Point, Hong Kong | 
         
        
                | Tel:
            (852) 2511 4261
                 | 
         
        
                | Fax:
            (852) 2588 1979
                 | 
         
        
                |  
                 | 
         
        
          | 
               
           | 
         
         
     |